Project Information:
Project Details:
Consultant: Transystems Corporation
Contractor: Barson Utilities, Inc.
Staff Contact: Cheryl Taylor, P.E., Civil Engineer, 817-748-8098 or 8100
What to expect in the next six months:
-
Construction began Summer 2009.
-
Construction will be limited to one location at a time until relocation of the utilities at that location is fully complete.
-
Traffic flow may be altered with the closure of one lane of traffic on FM 1709 during working hours.
-