Kirkwood Blvd. - N. Carroll Avenue Connector

 

Project Information:

This project involves funding for the design and construction of two concrete north lanes along Kirkwood Blvd. from the existing ending of Kirkwood Blvd. to Grace Lane. This project also involves the reconfiguration of two asphalt lanes along Highland St. west to Blythe to connect to Kirkwood Blvd. Funding will also include the reconfiguration of the Highland/Kirkwood intersection. This project is needed to facilitate travel to and from the new Carroll ISD middle school opening in Fall 2011.

  • This project began construction late November 2010 and is anticipated to be completed Fall 2011. 
  • Landscaping of the Kirkwood Blvd. medians is currently on hold until Stage 1 of Drought Contingency is lifted.

Project Details:

Engineering Consultant: Kimley Horn and Associates, Inc.

Contractor: Conatser Construction TX, L.P

Cost: $1,825,000

Staff Contact: Steve Anderson, P.E., Civil Engineer, 817-748-8101

Latest News:

Click here for the latest news about this project.