Roadway Connectors Parallel to Southlake Blvd
Project Information:
This project involves funding for the design and construction of the roadway connections from Westwood Dr. to S. Village Center Drive and from the Village Center Shopping Center to Southlake Corners. These connectors will improve vehicle connectivity parallel to Southlake Blvd. (FM 1709) following completion of the FM 1709 Median Project.
-
Westwood Connector
- Plans: 100 percent complete
- 24' roadway with sidewalks, and drainage improvements
- Construction is anticipated to begin in November 2011.
-
McPherson Connector
- Plans: 30 percent complete
- 24' roadway with sidewalks
Project Details:
Construction Contractor: TBD
Consultant: Halff Associates
Cost: $1,150,000
Staff contact: Steven D. Anderson, P.E., Civil Engineer, (817) 748-8101