Heatherwood and Royal Oaks and Twin Creeks Sanitary Sewer and Roadway Improvements

 

Note: Re-sodding and watering of existing grass in the right of way on the Neighborhood Sewer Project (NSP) is currently on hold until Stage 1 of Drought Contingency is lifted. Your patience is appreciated.

Project Information:

This Capital Improvement Program (CIP) project consists of the design and construction of approximately 8,000 linear feet of 8 inch sanitary sewer line to serve the Heatherwood, Royal Oaks, and Twin Creeks subdivisions. This project also includes the following:

  • Heatherwood Estates; includes the re-construction of Heatherbrook Ct. and Heather Ln.
  • Royal Oaks; includes the re-construction of Royal Oaks Ct.
  • Twin Creeks; includes the re-construction of Creekside Dr.
  • 1800 feet of sanitary sewer along E. Dove Rd.
  • Installation of a 12 inch water line along E. Dove Rd. from Lonesome Dove Rd. to N. Kimball Ave.
  • Re-construction of E. Dove Rd. from Lonesome Dove Rd. to N. Kimball Ave.
  • Drainage improvements along E. Dove Rd. from Lonesome Dove Rd. to N. Kimball Ave.
  • This project was bundled, bid and awarded with the improvements along Pearson Rd. and Primrose Lane.
  • Anticipated Completion: Spring 2012

 

Project Details:

Engineering Consultant: Cheatham & Associates

Contractor: North Texas Contracting

Staff Contact: Steve Anderson, P.E., Civil Engineer, 817-748-8101